Envirowatchers

[ Envirowatchers ] [ Main Menu ]


  


18137


Date: July 31, 2022 at 06:27:38
From: chatillon, [DNS_Address]
Subject: Big Louisiana coastal restoration projects continue

URL: https://www.msn.com/en-us/weather/topstories/big-louisiana-coastal-restoration-projects-continue/ar-AA107ZZr?ocid=msedgntp&cvid=7337f3eaf5ee403798667322b48d76ca


BELLE CHASSE, La. (AP) — Louisiana has completed one of
its biggest coastal restoration projects yet, and is at
work on even bigger ones.

The southwestern end of West Grand Terre Island in
Louisiana's Barataria Bay is shown on July 21, 2022;
the ruins of Fort Livingston are at the bottom left. On
Tuesday, July 26, 2022, the Coastal Protection and
Restoration Authority announced that it had completed
$100 million worth work to restore 251 acres of beach
and dune and 147 acres of back-barrier marsh on the
island. (AP Photo/Janet McConnaughey)
© Provided by Associated Press

The dredge used to suck up sediment from the Gulf of
Mexico to add 1,000 acres (405 hectares) of habitat to
sites in the Terrebonne Basin is now at work in the
Mississippi River, doing the same for a 1,600-acre
(650-hectare) project that's further east and named for
a historic Plaquemines Parish outlet called Spanish
Pass, officials said last week.

“These are key examples of our frontline defense”
against hurricanes, said Bren Haase, executive director
of the state Coastal Preservation and Restoration
Authority.

They had been eaten away by erosion and subsidence —
and by sea level rise, which, like hurricanes, is made
worse by climate change.

On Tuesday, the authority announced completion of
another project — the addition of about 256 acres (104
hectares) of beach and dune and 143 acres (58 hectares)
of marsh on West Grand Terre Island.

Barrier islands and marshes slow storm surge, so the
work protects people and buildings on shore while
providing habitat for plants and animals.

The Spanish Pass project starts just outside the
Plaquemines Parish town of Venice.

The fragility of the wetlands fringing Louisiana's
coast was illustrated less than a minute by seaplane
from the project's west end. In that spot, trees grow
in parallel lines on relatively high ground in open
water. They mark the banks of canals dredged through
marshes that no longer exist.

The state's biggest restoration project so far was
1,200 acres (485 hectares) completed in 2010 in the
upper Barataria Basin, the authority's deputy director,
Greg Grandy, said in an email. And work began in
January on the nearly 2,800-acre (1,100-hectare) Lake
Borgne Marsh Creation project near Shell Beach in St.
Bernard Parish.

“The more land I have between me, wherever I’m
standing, and the Gulf of Mexico as a hurricane is
approaching, the better I feel, the better off we are,”
Haase said. “Those natural barriers are very, very
important.”

The Terrebonne Basin project increased the size of
Timbalier and Trinity-East islands and West Belle
Headland as well as creating 8.6 miles (14 kilometers)
of beach. It took about two years, partly because of
hurricanes in 2020 and 2021.

Hurricane Zeta in 2020 and Hurricane Ida last year both
crossed the work area, Haase said.

He said work to enlarge Trinity East Island was
completed before Ida hit on Aug. 29, and it stood up
well to the storm. However, Ida damaged incomplete work
on West Belle Headland — an area that also had been
worked on in 2018 to repair damage from Hurricanes
Katrina and Rita in 2005.

The dredge is now working to create of seven miles of
marshes backed by ridges in an area west of Venice. The
ridges, high enough to be planted with trees, are
designed both to protect the new marshes from erosion
and to slow storm surges heading toward shore.

The project will take 10.8 million cubic yards (8.3
million cubic meters) of sediment — enough to fill the
Empire State Building nearly eight times.

Money paid by BP LLC after the 2010 oil spill is
funding the current projects.

The Terrebonne Basin project cost $166 million. The
Spanish Pass and West Belle Terre projects are about
$100 million each, the Lake Borgne project is about $61
million.

The Barataria project, completed about a month before
the spill, cost about $36 million.


Responses:
[18139]


18139


Date: July 31, 2022 at 07:02:02
From: chatillon, [DNS_Address]
Subject: Re: Big Louisiana coastal restoration projects continue - p.s.


The caption to the first picture in the article should
read PORT of Venice, La.
It is from small ports such as this that
fishing/shrimping boats as well as offshore production
vessels come and go.


Responses:
None


[ Envirowatchers ] [ Main Menu ]

Generated by: TalkRec 1.17
    Last Updated: 30-Aug-2013 14:32:46, 80837 Bytes
    Author: Brian Steele